| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 110619 | Sumidero tipo B | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| REJASB | Reja sumidero T-B (.50x.80) | un | 1.000000 | $218,915.00 | $218,915.00 |
| Suma de Material | $218,915.00 | ||||
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.264706 | $115,595.00 | $30,598.69 |
| Suma de Mano de Obra | $30,598.69 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| FORMASUM | Formaleta Sumidero A o B | día | 5.000000 | $3,480.00 | $17,400.00 |
| Suma de Equipo | $17,400.00 | ||||
| Auxiliar | |||||
| TRINT | Transporte interno | glo | 1.600000 | $1,000.00 | $1,600.00 |
| Suma de Auxiliar | $1,600.00 | ||||
| Concepto | |||||
| 050203 | Concreto 3000 psi en obra | m3 | 0.650000 | $294,870.00 | $191,665.50 |
| Suma de Concepto | $191,665.50 | ||||
| Costo Directo | $460,179.19 |