| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 110209 | Tubo concreto 20 uec. | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBOCONCRE19 | Tubo concreto sin refuerzo D=20" L=1.2m cl2 | ml | 1.030000 | $125,472.00 | $129,236.16 |
| ENSAYOT18 | Ensayo de tuberia | gl | 1.000000 | $1,259.00 | $1,259.00 |
| Suma de Material | $130,495.16 | ||||
| Mano de Obra | |||||
| ZCUADURB | Cuadrilla Urbanismo | jor | 0.143295 | $118,357.00 | $16,959.97 |
| Suma de Mano de Obra | $16,959.97 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| RETR1 | Retroexcavadora | hr | 0.066670 | $70,000.00 | $4,666.90 |
| Suma de Equipo | $4,666.90 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 2.584000 | $1,000.00 | $2,584.00 |
| Suma de Auxiliar | $2,584.00 | ||||
| Costo Directo | $154,706.03 |