| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 110202 | Tubo concreto 8 uec. | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBOCONCRE13 | Tubo concreto sin refuerzo D= 8" L=1.1m cl2 | ml | 1.030000 | $21,677.00 | $22,327.31 |
| ENSAYOT18 | Ensayo de tuberia | gl | 1.000000 | $1,259.00 | $1,259.00 |
| Suma de Material | $23,586.31 | ||||
| Mano de Obra | |||||
| ZCUADURB | Cuadrilla Urbanismo | jor | 0.030651 | $118,357.00 | $3,627.76 |
| Suma de Mano de Obra | $3,627.76 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRINT | Transporte interno | glo | 0.500000 | $1,000.00 | $500.00 |
| TRMAT | Transporte materiales | glo | 0.620000 | $1,000.00 | $620.00 |
| Suma de Auxiliar | $1,120.00 | ||||
| Costo Directo | $28,334.07 |