| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 05-1070 | CIMBRA COMUN EN CONTRATRABES DE CIMENTACION DE 20 X 80 CM. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 2.890000 | $12.74 | $36.82 |
| 1900-10 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 2.130000 | $12.74 | $27.14 |
| 1900-15 | MADERA DE PINO DE 3A. EN POLIN DE 3 1/2" X 3 1/2" | PT | 0.780000 | $6.25 | $4.88 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.090000 | $18.93 | $1.70 |
| 0085-00 | VARILLA FY=4200 KG/CM2 NO. 4 ( 1/2" ) | KG | 1.000000 | $10.43 | $10.43 |
| 0950-05 | DIESEL | LT | 0.500000 | $5.41 | $2.71 |
| Suma de Material | $83.68 | ||||
| Mano de Obra | |||||
| 02-0590 | CUADRILLA No 59 ( 1 CARPINTERO DE OBRA NEGRA + 1 AYUDANTE DE CARPINTERIA OBRA NEGRA ) | JOR | 0.144300 | $768.29 | $110.86 |
| Suma de Mano de Obra | $110.86 | ||||
| Costo Directo | $194.54 |