| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 180302 | Espejo | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ESPEJ | Espejo 4 mm | m2 | 1.000000 | $51,854.00 | $51,854.00 |
| PEGAN05 | Pegante boxer | un | 0.050000 | $30,881.00 | $1,544.05 |
| Suma de Material | $53,398.05 | ||||
| Mano de Obra | |||||
| ZCUADINS | Cuadrilla Instalaciones | jor | 0.014000 | $116,803.00 | $1,635.24 |
| Suma de Mano de Obra | $1,635.24 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 2.000000 | $1,000.00 | $2,000.00 |
| Suma de Auxiliar | $2,000.00 | ||||
| Costo Directo | $57,033.29 |