| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3 | SUMINISTRO Y COLOCACION DE LOSACERO SECCION 4CALIBRE 22 EN MEZZANINES | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| LOSACERO CAL. 22 | LOSACERO CAL. 22 | M2 | 1.100000 | $112.00 | $123.20 |
| ACETILENO | ACETILENO | M3 | 0.010350 | $65.00 | $0.67 |
| OXIGENO | OXIGENO | M3 | 0.016750 | $45.00 | $0.75 |
| SOLDADURA E7018 | SOLDADURA E7018 | KG | 0.028500 | $35.00 | $1.00 |
| FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.035000 | $0.00 | $0.00 |
| Suma de Material | $125.62 | ||||
| Mano de Obra | |||||
| CUADRILLA-SAMS-32 | 1 OFICIAL TECHADOR + 5 AYUDANTES | JOR | 0.007340 | $1,526.47 | $11.20 |
| Suma de Mano de Obra | $11.20 | ||||
| Equipo | |||||
| EQUIPO DE OXICORTE | EQUIPO DE OXICORTE | HR | 0.013870 | $10.82 | $0.15 |
| SOLDADORA EST. | Soldadora Miller Dimension Mod. 652 | HR | 0.006190 | $31.60 | $0.20 |
| Suma de Equipo | $0.35 | ||||
| Costo Directo | $137.17 |