| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 050600 | Alfajias de concreto (15-25 cm) | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.080970 | $115,595.00 | $9,359.73 |
| Suma de Mano de Obra | $9,359.73 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| OBRAFALSA | Obra falsa (alquiler) | dÃa | 0.243070 | $4,365.00 | $1,061.00 |
| FORMALETA | Formaleta | gl | 3.000000 | $1,000.00 | $3,000.00 |
| Suma de Equipo | $4,061.00 | ||||
| Concepto | |||||
| 050203 | Concreto 3000 psi en obra | m3 | 0.048150 | $294,870.00 | $14,197.99 |
| 050208 | Mortero 1: 3 de pega | m3 | 0.006420 | $333,881.00 | $2,143.52 |
| Suma de Concepto | $16,341.51 | ||||
| Costo Directo | $29,762.23 |