| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 110623 | Caja de inspeccion 60 x 60 | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| HERRACAJA04 | Herraje caja inspeccion 60*60 | un | 1.000000 | $93,388.00 | $93,388.00 |
| Suma de Material | $93,388.00 | ||||
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.568680 | $115,595.00 | $65,736.56 |
| Suma de Mano de Obra | $65,736.56 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.066000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRLOC | Transporte local | m3 | 0.220500 | $5,000.00 | $1,102.50 |
| Suma de Auxiliar | $1,102.50 | ||||
| Concepto | |||||
| 050104 | Formaleta caja inspeccion 60x60. | un | 1.000000 | $12,434.00 | $12,434.00 |
| 050203 | Concreto 3000 psi en obra | m3 | 0.220500 | $294,870.00 | $65,018.84 |
| 050216 | Mortero 1:4 de revoque | m3 | 0.010000 | $276,729.00 | $2,767.29 |
| 040206 | Refuerzo de 60.000 psi | kg | 6.000000 | $2,910.00 | $17,460.00 |
| Suma de Concepto | $97,680.13 | ||||
| Costo Directo | $257,907.19 |