| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 090130 | Piso en mortero 1:4 e=0.05m | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| ZCUADPIS | Cuadrilla Pisos | jor | 0.029500 | $121,896.00 | $3,595.93 |
| Suma de Mano de Obra | $3,595.93 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| VIBRADOR01 | Vibrador de concreto, electrico a 110v (alquiler) | día | 0.020000 | $34,452.00 | $689.04 |
| FORMALETA | Formaleta | gl | 3.000000 | $1,000.00 | $3,000.00 |
| Suma de Equipo | $3,689.04 | ||||
| Auxiliar | |||||
| TRLOC | Transporte local | m3 | 0.055000 | $5,000.00 | $275.00 |
| Suma de Auxiliar | $275.00 | ||||
| Concepto | |||||
| 050209 | Mortero 1: 4 de pega | m3 | 0.055000 | $285,872.00 | $15,722.96 |
| Suma de Concepto | $15,722.96 | ||||
| Costo Directo | $23,282.93 |