| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 130109 | Acometida 3#2+2#8 tubo pvc 3" | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBOPVCO60 | Tubo pvc-conduit 3" - Pavco | ml | 1.000000 | $50,477.00 | $50,477.00 |
| CABLECOBT02/0 | Cable cobre THHN/THWN 2/0 awg | ml | 4.000000 | $26,488.00 | $105,952.00 |
| CABLECOBT08 | Cable cobre THHN/THWN 8 awg | ml | 1.000000 | $3,518.00 | $3,518.00 |
| VARIO | Varios electricos | un | 0.970000 | $1,318.00 | $1,278.46 |
| Suma de Material | $161,225.46 | ||||
| Mano de Obra | |||||
| ZCUADIEL | Cuadrilla Instalaciones Eléctricas | jor | 0.059004 | $116,803.00 | $6,891.84 |
| Suma de Mano de Obra | $6,891.84 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $168,117.30 |