| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 130206 | Bajante 3#2/0+1/0 cu-thw 3" | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBOGA35 | Tubo galvanizado 3" | un | 6.000000 | $51,301.00 | $307,806.00 |
| CABLEAC01/0 | Cable acsr # 1/0 | ml | 10.000000 | $1,792.00 | $17,920.00 |
| CABLECOBT02/0 | Cable cobre THHN/THWN 2/0 awg | ml | 30.000000 | $26,488.00 | $794,640.00 |
| CONECTOR30 | Conector tornillo partido KS-26 2/0 | un | 3.000000 | $9,540.00 | $28,620.00 |
| VARIO | Varios electricos | un | 12.656000 | $1,318.00 | $16,680.61 |
| Suma de Material | $1,165,666.61 | ||||
| Mano de Obra | |||||
| ZCUADIEL | Cuadrilla Instalaciones Eléctricas | jor | 0.270434 | $116,803.00 | $31,587.50 |
| Suma de Mano de Obra | $31,587.50 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $1,197,254.11 |