| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 210836 | Palma Alejandra h=2.0m | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ARBOLPALMAALEJ | Arbol palma alejandra h=2.0m | un | 1.000000 | $130,500.00 | $130,500.00 |
| TIERRA | Tierra abonada | m3 | 0.850000 | $65,517.00 | $55,689.45 |
| Suma de Material | $186,189.45 | ||||
| Mano de Obra | |||||
| ZCUADURB | Cuadrilla Urbanismo | jor | 0.322390 | $118,357.00 | $38,157.11 |
| Suma de Mano de Obra | $38,157.11 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 5.000000 | $1,000.00 | $5,000.00 |
| Suma de Auxiliar | $5,000.00 | ||||
| Costo Directo | $229,346.56 |