| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 070110 | Sobrecimiento bloque 15 dos hiladas | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BLOQCON15B | Bloque concreto 15x20x40 | un | 5.500000 | $1,937.00 | $10,653.50 |
| Suma de Material | $10,653.50 | ||||
| Mano de Obra | |||||
| ZCUADMAM | Cuadrilla MamposterÃa | jor | 0.027600 | $116,803.00 | $3,223.76 |
| Suma de Mano de Obra | $3,223.76 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRINT | Transporte interno | glo | 0.276000 | $1,000.00 | $276.00 |
| TRMAT | Transporte materiales | glo | 1.093000 | $1,000.00 | $1,093.00 |
| Suma de Auxiliar | $1,369.00 | ||||
| Concepto | |||||
| 050209 | Mortero 1: 4 de pega | m3 | 0.010000 | $285,872.00 | $2,858.72 |
| 050201 | Concreto 2000 psi en obra | m3 | 0.022000 | $261,470.00 | $5,752.34 |
| Suma de Concepto | $8,611.06 | ||||
| Costo Directo | $23,857.32 |