| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 110611 | Cono, cuello, tapa, base Man hole | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONOP1.2 | Cono pref manhole 1.20m, concentrico | un | 1.000000 | $286,520.00 | $286,520.00 |
| CUELLO02 | Cuello pref manhole | un | 1.000000 | $141,633.00 | $141,633.00 |
| TAPAMH | Tapa prefabricada manhole | un | 1.000000 | $105,053.00 | $105,053.00 |
| Suma de Material | $533,206.00 | ||||
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.066845 | $115,595.00 | $7,726.95 |
| Suma de Mano de Obra | $7,726.95 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| FORMALETA | Formaleta | gl | 20.000000 | $1,000.00 | $20,000.00 |
| Suma de Equipo | $20,000.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 5.000000 | $1,000.00 | $5,000.00 |
| Suma de Auxiliar | $5,000.00 | ||||
| Concepto | |||||
| 050209 | Mortero 1: 4 de pega | m3 | 0.097660 | $285,872.00 | $27,918.26 |
| 050203 | Concreto 3000 psi en obra | m3 | 0.093490 | $294,870.00 | $27,567.40 |
| 170207 | Anticorrosivo escalon | ml | 1.000000 | $4,321.00 | $4,321.00 |
| Suma de Concepto | $59,806.66 | ||||
| Costo Directo | $625,739.60 |