| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 129 | CARGA MANUAL Y ACARREO HASTA 50.0 m EN CARRETILLA DEL MATERIAL SOBRANTE DE LAS EXCAVACIONES (VOL. MEDIO SUELTO). INCLUYE SUMINISTRO Y USO DE HERRAMIENTA, EQUIPO, MANO DE OBRA Y LIMPIEZA FINAL. PLANOS DE REFERENCIA: D-CPTGA-X-301, D-CPTGA-X-302, D-CPTGA-F-303, B-CPTGA-X-303, B-CPTGA-X-304, D-CPTGA-P1-F-101, D-CPTGA-P2-F-101, D-CPTGA-P3-F-101, D-CPTGA-P4-F-101, D-CPTGA-P5-F-101, D-CPTGA-P6-F-101, D-CPTGA-P7-F-101, D-CPTGA-AL-1-F-101, D-CPTGA-AL-2-F-101. ALCANCES DE ACUERDO AL ANEXO BP " | M³ |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| C004SGP | TRAPO LIMPIO DE ALGODON | KG | 0.010000 | $26.50 | $0.27 |
| Suma de Material | $0.27 | ||||
| Mano de Obra | |||||
| CUA05 | CUADRILLA DE OBREROS | JOR | 0.020000 | $799.18 | $15.98 |
| Suma de Mano de Obra | $15.98 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)MO | 0.025000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)MO | 0.025000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| CARRE | CARRETILLAS PARA ACARREO DE MATERIAL MARCA TRUPER MODELO 65D | HORA | 0.050000 | $2.47 | $0.12 |
| Suma de Equipo | $0.12 | ||||
| Costo Directo | $16.37 |