| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IM01-25 | CONSTRUCCION DE IMBORNAL DE 1.20 x 0.60 x 1.30 M DE PROFUNDIDAD EN MURO DE 10 CM DE ESPESOR CON CONCRETO F'c=200 KG/CM2 ARMADO CON Vs # 3 @ 15 CM EN AMBOS SENTIDOS (INCLUYE CIMBRA, COLADOS, ETC.) CON REJA METALICA DE ANGULO DE 3" x 3/16" | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO ESTR 1 | ACERO ESTRUCTURAL EN VIGAS Y CANAL | KG | 144.020000 | $20.00 | $2,880.40 |
| SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 4.000000 | $49.88 | $199.52 |
| OXIGENO 1 | OXIGENO | M3 | 1.000000 | $39.00 | $39.00 |
| ACETILENO 1 | ACETILENO | KG | 1.000000 | $130.00 | $130.00 |
| Suma de Material | $3,248.92 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.025000 | $290.45 | $7.26 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.250000 | $233.90 | $58.48 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.250000 | $181.41 | $45.35 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.500000 | $169.01 | $84.51 |
| Suma de Mano de Obra | $195.59 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| SOLDADORA 300 AMP 1 | SOLDADORA LINCOLN 300 AMP MOTOR DIESEL DE 60 HP | HORA | 1.500000 | $111.52 | $167.28 |
| EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 1.500000 | $24.34 | $36.51 |
| Suma de Equipo | $203.79 | ||||
| Auxiliar | |||||
| TRAZO Y NIVELACION 1 | TRAZO Y NIVELACION | M2 | 0.720000 | $3.99 | $2.87 |
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 4.992000 | $68.74 | $343.15 |
| PLAN CONCR 1 | PLANTILLA CONCRETO F'c=100 | M2 | 0.910000 | $78.79 | $71.70 |
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 34.580000 | $22.84 | $789.81 |
| CIMBRA COMUN 1 | CIMBRA COMUN | M2 | 9.880000 | $112.45 | $1,111.01 |
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 0.610000 | $1,311.84 | $800.22 |
| RELLENO APISONADO 1 | RELLENO APISONADO | M3 | 3.809000 | $40.09 | $152.70 |
| ACARREO KMS 1 | ACARREO 1er KM CAMION | M3 | 5.140000 | $76.52 | $393.31 |
| ACARREO KMS 2 | ACARREO KMS SUBSECUENTES AL 1er | M3-KM | 25.700000 | $7.11 | $182.73 |
| LIMPIEZA GRAL 1 | LIMPIEZA GENERAL DE LA OBRA | M2 | 0.910000 | $3.90 | $3.55 |
| Suma de Auxiliar | $3,851.05 | ||||
| Costo Directo | $7,499.35 |