| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4002-02 | DETALLE DE BASE DE TUBO PVC DE 24" CONCRETRO F'C=250 KG/CM2 DE 1.00 x 0.30 x 0.12 M MALLA ELECTROSOLDADA 66/6-6 EN AMBOS SENTIDOS INCLUYE CIMBRADO Y DESCIMBRADO Y ARMEX 20x15x4 | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MALLA ELEC 6-6/6-6 1 | MALLA ELECTROSOLDADA 6-6/6-6 | M2 | 1.100000 | $33.86 | $37.25 |
| ARMEX 15*20-4 | ARMEX 15-20-4 | M | 2.000000 | $31.00 | $62.00 |
| Suma de Material | $99.25 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.015000 | $290.45 | $4.36 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.150000 | $233.90 | $35.09 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.150000 | $181.41 | $27.21 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.150000 | $169.01 | $25.35 |
| Suma de Mano de Obra | $92.00 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| CIMBRA APARENTE 1 | CIMBRA APARENTE EN MURO | M2 | 1.600000 | $196.64 | $314.62 |
| CONCRETO F-C=250 1 | CONCRETO F'c=250 KG/CM2 | M3 | 0.192000 | $1,407.27 | $270.20 |
| VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.192000 | $215.24 | $41.33 |
| Suma de Auxiliar | $626.15 | ||||
| Costo Directo | $817.40 |