| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4022-10 | ESTRUCTURA DE PRETIL Y FALDON FABRICADA CON COVINTEC CON ALTURA DE 1.25 M, AMARRADA A ESTRUCTURA DE LOSA DE TECHO, INCLUYE ALINEADO Y PLOMEADO, MATERIALES, MANO DE OBRA, EQUIPO Y HERRAMIENTA | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PANEL COVINTEC 2" 1 | PANEL COVINTEC DE 2" | M | 1.100000 | $49.00 | $53.90 |
| MALLA ESQ 4"X4" | MALLA ESQUINERO DE 4" x 4" | M | 1.100000 | $35.00 | $38.50 |
| ACERO DE REF 3/8" 1 | ACERO DE REFUERZO DE 3/8" | KG | 0.400000 | $14.08 | $5.63 |
| ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.100000 | $19.00 | $1.90 |
| Suma de Material | $99.93 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.008500 | $290.45 | $2.47 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.085000 | $233.90 | $19.88 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.085000 | $181.41 | $15.42 |
| Suma de Mano de Obra | $37.77 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $137.70 |