| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3080-07 | POZO PREFABRICADO DE CONCRETO ARMADO DE 6.00 M DE PROFUNDIDAD A BASE DE SECCIONES DE 1.22 INCLUYE BASE, SECCIONES Y CONO, SELLADO CON LIGA Y ESCALONES PREFABRICADO | POZO |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BASE PREF 1.22 M 1 | BASE PREF CONCRETO P/POZO DE 1.22 M DIAM | PZA | 1.000000 | $3,730.00 | $3,730.00 |
| INTER PREF 1.22 M 1 | INTERMEDIO PREF CONCRETO P/POZO DE 1.22 M ALT | PZA | 3.000000 | $3,172.00 | $9,516.00 |
| INTER PREF 0.61 M 1 | INTERMEDIO PREF CONCRETO P/POZO DE 0.61 M ALT | PZA | 1.000000 | $1,760.00 | $1,760.00 |
| CONO PREF 0.61 M 1 | CONO PREF CONCRETO P/POZO DE 0.61 M ALT | PZA | 1.000000 | $1,760.00 | $1,760.00 |
| TAPA Y BROCAL CONC | TAPA Y BROCAL CONCRETO P/POZO PREF | JGO | 1.000000 | $1,300.00 | $1,300.00 |
| ESCALON PREFRAB 1 | ESCALON PREFABRICADO | PZA | 20.000000 | $155.00 | $3,100.00 |
| FESTERPLAST 1 | FESTERPLAST | CUBETA | 0.600000 | $1,476.00 | $885.60 |
| Suma de Material | $22,051.60 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.175000 | $290.45 | $50.83 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 1.750000 | $233.90 | $409.33 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 1.750000 | $181.41 | $317.47 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 2.750000 | $169.01 | $464.78 |
| Suma de Mano de Obra | $1,242.40 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| CAMION HIAB 1 | CAMION CON BRAZO HIAB DE 5 TON DE CAPACIDAD | HORA | 4.500000 | $386.00 | $1,737.00 |
| Suma de Equipo | $1,737.00 | ||||
| Auxiliar | |||||
| CONCRETO F-C=150 1 | CONCRETO F'c=150 KG/CM2 | M3 | 0.150000 | $1,170.99 | $175.65 |
| CIM Y DESCIM 1 | CIMBRA Y DESCIMBRA | M2 | 1.500000 | $159.93 | $239.90 |
| Suma de Auxiliar | $415.54 | ||||
| Costo Directo | $25,446.54 |