| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 6.13.4 | SUMINISTRO E INSTALACION DE COPLE PVC INGL DE 4" C-40 CEM | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0303101 | COPLE HID CEM. 100 MM | PZ | 1.000000 | $22.99 | $22.99 |
| 9700130 | LIMPIADOR REXOLIT .500 LTS. | PZ | 0.157000 | $8.82 | $1.38 |
| 9700254 | CEMENTO AGRICOLA 480 ML | PZ | 0.261000 | $24.80 | $6.47 |
| Suma de Material | $30.85 | ||||
| Mano de Obra | |||||
| 1I1EI | CUADRILLA No.24 (1.00 OF. INST.+ 1.00 AY.ESP.) | jor | 0.025600 | $749.35 | $19.18 |
| Suma de Mano de Obra | $19.18 | ||||
| Herramienta | |||||
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AMAPE-039INS2 | CAMIONETA PICK UP MCA NISSAN | hora | 0.012050 | $164.54 | $1.98 |
| Suma de Equipo | $1.98 | ||||
| Costo Directo | $52.01 |