| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 46 | CASTILLO DE CONCRETO SECCION= 15 X 15 CM, CONCRETO F'C=150 KG/CM2-3/4", CIMBRA 3 CARAS, REFORZADO CON 4 VARILLAS R.N. DE 3/8" ESTRIBOS DE 1/4" A/C 25 CM | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA 04 | MADERA PINO 3a. | PT | 3.000000 | $6.00 | $18.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.100000 | $23.38 | $2.34 |
| 1.-COMBDIESE | Diesel | Lt | 0.500000 | $5.40 | $2.70 |
| ACERO-006 | ACERO DE DIFERENTES MEDIDAS | TON | 0.003110 | $9,035.00 | $28.10 |
| ACERO-18 | ALAMBRE RECOCIDO | Kg | 0.200000 | $14.87 | $2.97 |
| CIMBRA 01 | TRIPLAY DE 3/4" 2.44 x 1.22 m. | M2 | 0.472500 | $114.00 | $53.87 |
| Suma de Material | $107.98 | ||||
| Mano de Obra | |||||
| CUADRILLA ALBAÑIL-5 | (1 Of. Albanil + 5 Peones). | JOR | 0.066667 | $1,207.38 | $80.49 |
| Suma de Mano de Obra | $80.49 | ||||
| Auxiliar | |||||
| CONCRETO 150 KG/CM2 | CONCRETO DE F'C= 150KG/CM2 HECHO EN OBRA AGREGADO MAXIMO 3/4. | M3 | 0.023175 | $840.13 | $19.47 |
| Suma de Auxiliar | $19.47 | ||||
| Costo Directo | $207.94 |