Pavimentadora Barber Green SB 131 motor John Deere diesel 4276-T de 95 HP turbo ancho 3.0 m -6.10m; vel. pav. 33-95 m/min.

Clave Descripción del costo horario Unidad
CHC111 Pavimentadora Barber Green SB 131 motor John Deere diesel 4276-T de 95 HP turbo ancho 3.0 m -6.10m; vel. pav. 33-95 m/min. hr
DATOS GENERALES
Vad = VALOR DE ADQUISICIÓN $3,088,786.07 Pnom = POTENCIA NOMINAL 95.000000 H.P.
Pn = VALOR DE LAS LLANTAS $0.00 Fo = FACTOR DE OPERACION 1.0000
Pa = VALOR DE PIEZAS ESPECIALES $0.00 TIPO DE COMBUSTIBLE Diesel
Vm = VALOR NETO $3,088,786.07 Cco = COEFICIENTE DE COMBUSTIBLE 0.1
Vr = VALOR DE RESCATE $617,757.21 Pc = PRECIO DEL COMBUSTIBLE $11.07 /LITRO
i = TASA DE INTERES 16.000000 /AÑO Cc = CAPACIDAD DEL CARTER 0.00 LITROS
s = PRIMA DE SEGUROS 3.000000 /AÑO Tc = TIEMPO ENTRE CAMBIO DE ACEITE 0 HORAS
Ko = FACTOR DE MANTENIMIENTO 0.650000 HORAS Fl = FACTOR DE LUBRICANTE 0
Ve = VIDA ECONÓMICA 8,000.00 HORAS Pac = PRECIO DEL ACEITE /LITRO
Vn = VIDA ECONÓM. DE LAS LLANTAS 0.00 HORAS Gh=CANTIDAD DE COMBUSTIBLE = Cco*Fo*Pnom 9.500000 LITROS/HORA
Va = VIDA ECONOM. PIEZAS ESPECIALES 0.00 HORAS Ah=CANTIDAD DE LUBRICANTE = Fl*Fo*Pnom 0.000000 LITROS/HORA
Hea = HORAS TRABAJADAS POR AÑO 1,000.00 HORAS Ga=CONSUMO ENTRE CAMBIOS DE LUBRICANTE = Cc/Tc 0.000000 LITROS/HORA
Ht = Horas por turno 6.400000 Ht = HORAS
CONCEPTO OPERACIONES ACTIVO EN ESPERA EN RESERVA
COSTOS FIJOS
DEPRECIACIÓN (D) = (Vm-Vr)/Ve (3088786.07-617757.21)/8000.00 $308.88 $247.10 $247.10
INVERSIÓN (Im) = [(Vm+Vr)/2Hea]i [(3088786.07+617757.21)/(2*1000.00)]0.160000 $296.52 $296.52 $296.52
SEGURO (Sm) = [(Vm+Vr)/2Hea]s [(3088786.07+617757.21)/(2*1000.00)]0.030000 $55.60 $55.60 $55.60
MANTENIMIENTO (Mn) = Ko * D 0.650000*308.88 $200.77 $200.77 $160.62
Costos fijos $861.77 $799.99 $759.84
CARGOS POR CONSUMO
COMBUSTIBLE Co = GhxPc 9.500000*11.07 $105.17 $31.55 $0.00
OTRAS FUENTES DE ENERGÍA 0*0 $0.00 $0.00 $0.00
LUBRICANTES Lb = (Ah+Ga)Pac (0+0)0 $0 $0 $0
LLANTAS = Pn/Vn 0/0 $0.00 $0.00 $0.00
PIEZAS ESPECIALES = Pa/Va 0/0 $0.00 $0.00 $0.00
Cargos por consumo $105.17 $31.55 $0.00
CARGOS POR OPERACIÓN
CATEGORÍA CANTIDAD SALARIO REAL Ht ACTIVO EN ESPERA EN RESERVA
Operador de equipo mayor 1 $627.86 6.400000 $98.10 $0.00 $0.00
SUMA (Sr) $627.86 6.400000 $98.10 $0.00 $0.00
Cargos por operación (Sr/Ht) $98.10 $0 $0
Costo Directo por Hora $1065.04 $831.54 $759.84