| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| TB-FBCM-0300 | Tubo de fibrocemento de 300mm, 12", clase a-7, concople y junta de hule, eureka, incluye materiales,desperdicios, mano de obra y herramienta menor | m |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| MAC-1170 | Tubo fibrocemento de 300 mm.12".a-7 | trm | 0.262500 | $2,024.12 | $531.33 |
| MAC-1165 | Grasa multilitio no, 2 p/maquinaria | kg | 0.021500 | $17.26 | $0.37 |
| MAC-928 | Estopa alquitranada | kg | 0.006100 | $30.44 | $0.19 |
| MAC-1170 | Tubo fibrocemento de 300 mm.12".a-7 | trm | 0.262500 | $2,024.12 | $531.33 |
| MAC-1165 | Grasa multilitio no, 2 p/maquinaria | kg | 0.021500 | $17.26 | $0.37 |
| MAC-928 | Estopa alquitranada | kg | 0.006100 | $30.44 | $0.19 |
| Suma de Material | $1,063.78 | ||||
| Mano de Obra | |||||
| AUXCDTR-101 | 0 | jor | 0.117600 | $6,394.20 | $751.96 |
| AUXCDTR-101 | 0 | jor | 0.117600 | $6,394.20 | $751.96 |
| Suma de Mano de Obra | $1,503.92 | ||||
| Herramienta | |||||
| HEC-001 | Herramienta menor | %mo | 3.000000 | $0.00 | $0.00 |
| HEC-003 | Equipo mayor | %mo | 5.000000 | $0.00 | $0.00 |
| HEC-001 | Herramienta menor | %mo | 3.000000 | $0.00 | $0.00 |
| HEC-003 | Equipo mayor | %mo | 5.000000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| EQC-037 | Camioneta chasis cabina de 3.5 ton | hr | 0.015500 | $399.66 | $6.19 |
| EQC-037 | Camioneta chasis cabina de 3.5 ton | hr | 0.015500 | $399.66 | $6.19 |
| Suma de Equipo | $12.38 | ||||
| Costo Directo | $2,580.08 |