Material |
|
|
|
|
MAC-018 |
Madera pino 3a, 1″ x 4″ x 8.25′ |
pt |
0.001500 |
$9.33 |
$0.01 |
MAC-019 |
Madera pino 3a, 2″ x 4″ x 8.25′ |
pt |
0.002500 |
$9.33 |
$0.02 |
MAC-005 |
Cal hl datada, saco 25 kg |
ton |
0.000200 |
$1,575.08 |
$0.32 |
MAC-021 |
Carrete de hilo plastico |
m |
0.350000 |
$0.24 |
$0.08 |
MAC-022 |
Pintura de esmalte comex 100, comex |
cub |
0.000100 |
$1,242.64 |
$0.12 |
MAC-024 |
Acero de refuerzo numero 4, 1/2m |
kg |
0.010100 |
$9.97 |
$0.10 |
MAC-020 |
Clavo de 2 1/2″ (6.35cm) de largo |
kg |
0.000500 |
$21.90 |
$0.01 |
MAC-018 |
Madera pino 3a, 1″ x 4″ x 8.25′ |
pt |
0.001500 |
$9.33 |
$0.01 |
MAC-019 |
Madera pino 3a, 2″ x 4″ x 8.25′ |
pt |
0.002500 |
$9.33 |
$0.02 |
MAC-005 |
Cal hl datada, saco 25 kg |
ton |
0.000200 |
$1,575.08 |
$0.32 |
MAC-021 |
Carrete de hilo plastico |
m |
0.350000 |
$0.24 |
$0.08 |
MAC-022 |
Pintura de esmalte comex 100, comex |
cub |
0.000100 |
$1,242.64 |
$0.12 |
MAC-024 |
Acero de refuerzo numero 4, 1/2m |
kg |
0.010100 |
$9.97 |
$0.10 |
MAC-020 |
Clavo de 2 1/2″ (6.35cm) de largo |
kg |
0.000500 |
$21.90 |
$0.01 |
|
Suma de Material |
|
|
|
$1.32 |
|
Mano de Obra |
|
|
|
|
AUXCDTR-055 |
Cuadrilla 55 (oficial albañil y dos peones), incluye maestro y mando intermedio |
jor |
0.003300 |
$2,668.52 |
$8.81 |
AUXCDTR-055 |
Cuadrilla 55 (oficial albañil y dos peones), incluye maestro y mando intermedio |
jor |
0.003300 |
$2,668.52 |
$8.81 |
|
Suma de Mano de Obra |
|
|
|
$17.62 |
|
Herramienta |
|
|
|
|
HEC-001 |
Herramienta menor |
%mo |
3.000000 |
$0.00 |
$0.00 |
HEC-001 |
Herramienta menor |
%mo |
3.000000 |
$0.00 |
$0.00 |
|
Suma de Herramienta |
|
|
|
$0.00 |
|
Equipo |
|
|
|
|
EQC-003 |
Nivel para medicion k-e, tipo dumpy |
hr |
0.019500 |
$447.07 |
$8.72 |
EQC-004 |
Transito para medicion k-e, modelo |
hr |
0.019500 |
$447.69 |
$8.73 |
EQC-003 |
Nivel para medicion k-e, tipo dumpy |
hr |
0.019500 |
$447.07 |
$8.72 |
EQC-004 |
Transito para medicion k-e, modelo |
hr |
0.019500 |
$447.69 |
$8.73 |
|
Suma de Equipo |
|
|
|
$34.90 |
|
Auxiliar |
|
|
|
|
AUXCNRN-100 |
Concreto f’c= 100 kg/cm2, fabricado en obra, resistencia normal, agregado maximo de 3/4″, incluye materiales, desperdicios, mano de obra y equipo, revenimiento de 8 a 10 cm |
m3 |
0.001200 |
$1,933.94 |
$2.32 |
AUXCNRN-100 |
Concreto f’c= 100 kg/cm2, fabricado en obra, resistencia normal, agregado maximo de 3/4″, incluye materiales, desperdicios, mano de obra y equipo, revenimiento de 8 a 10 cm |
m3 |
0.001200 |
$1,933.94 |
$2.32 |
|
Suma de Auxiliar |
|
|
|
$4.64 |
|
Costo Directo |
|
|
|
$58.48 |