| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| E05.035 | Guarnición de concreto f'c=150 kg/cm2 de 10x36 cm armado con 4 varillas No.3 alta resistencia, estribos del No.2 @ 25 cm, acabado pulido redondeado. | m |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| MATE-20 | Alambrón liso de 1/4" (No.2) | kg | 0.966000 | $11.00 | $10.63 |
| MATE-540 | Varilla fy=4200 kg/cm2 No.3 (3/8") | kg | 1.613000 | $9.50 | $15.32 |
| MATE-19 | Alambre recocido del No.18 | kg | 0.067000 | $12.50 | $0.84 |
| Suma de Material | $26.79 | ||||
| Mano de Obra | |||||
| 00-M0005 | Cuadrila 05 (Albañil + 2 Ayudantes) | jor | 0.212819 | $1,147.64 | $244.24 |
| Suma de Mano de Obra | $244.24 | ||||
| Auxiliar | |||||
| E00.020 | Mortero cemento-arena 1:5 | m3 | 0.008000 | $817.93 | $6.54 |
| E00.016 | Concreto f'c=150 kg/cm2 | m3 | 0.037800 | $1,073.49 | $40.58 |
| E00.011 | Cimbra en cadenas y castillos | m2 | 0.720000 | $135.95 | $97.88 |
| Suma de Auxiliar | $145.00 | ||||
| Costo Directo | $416.03 |