| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| A10085A025 | Poste conc comun 12.5x12.5cm, conc f'c=150kg/cm2, armex 10.10.3 | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Mano de Obra | |||||
| 1AA00 | Peón | Jor | 0.025000 | $227.31 | $5.68 |
| 1AABO | Albañil | Jor | 0.025000 | $372.63 | $9.32 |
| 1AZC1 | Cabo de oficiales | jor | 0.002500 | $518.10 | $1.30 |
| Suma de Mano de Obra | $16.30 | ||||
| Herramienta | |||||
| 2HER | Herramienta menor | (%)mo | 0.000300 | $16.30 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| HA176 | Vaciado, colado, vibrado cadenas y castillos | m3 | 0.016100 | $311.95 | $5.02 |
| Suma de Auxiliar | $5.02 | ||||
| Concepto | |||||
| HA163 | Cimbra comun cadenas y castillos | m2 | 0.125000 | $113.49 | $14.19 |
| HA162 | Suministro, habilitado, colocacion armex estruc 10x10-3 fy=6200 kg/cm2 | m | 1.854000 | $15.11 | $28.01 |
| HA171 | Concreto f'c=150 kg/cm2, r.n., tma 19mm (3/4"), hecho en obra c/revolvedora | m3 | 0.016100 | $755.68 | $12.17 |
| Suma de Concepto | $54.37 | ||||
| Costo Directo | $75.69 |