| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| A25010A195 | Subdrenes tubos perforados, p.u.o.t. de p.v.c., ensubdrenes transversales de penetracion: -de 51 mm.(2") de diametro y 12.00 m. de longitud. | m |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| BTUPVC0496 | Tuberia pvc sanit 51mm (2") diam. | PZA | 2.000000 | $70.79 | $141.58 |
| LSATF085 | Cople pvc sanitario 50mm cementar | pza | 1.000000 | $1.30 | $1.30 |
| BPINT0217 | Pegamento pvc oatey 500 grs. | grs | 0.066700 | $8.22 | $0.55 |
| Suma de Material | $143.43 | ||||
| Mano de Obra | |||||
| 1ATBO | Tubero | Jor | 0.050000 | $379.35 | $18.97 |
| 1AA01 | Ayudante general | Jor | 0.050000 | $229.51 | $11.48 |
| 1AZC1 | Cabo de oficiales | jor | 0.005000 | $518.10 | $2.59 |
| Suma de Mano de Obra | $33.04 | ||||
| Herramienta | |||||
| 2HER | Herramienta menor | (%)mo | 0.000300 | $33.04 | $0.01 |
| Suma de Herramienta | $0.01 | ||||
| Costo Directo | $176.48 |