| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| A25025A105 | Tubo de concreto simpled e 15 cm, junteado con mortero cemento-arena 1:4. | m |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| BIEXX036 | Tubo de albañal de 15 cms (6") | pza | 1.050000 | $36.52 | $38.35 |
| ACMXX005 | Agua | m3 | 0.045000 | $85.00 | $3.83 |
| Suma de Material | $42.18 | ||||
| Mano de Obra | |||||
| 1AABO | Albañil | Jor | 0.063300 | $372.63 | $23.59 |
| 1AA00 | Peón | Jor | 0.063300 | $227.31 | $14.39 |
| 1AZC1 | Cabo de oficiales | jor | 0.006300 | $518.10 | $3.26 |
| Suma de Mano de Obra | $41.24 | ||||
| Herramienta | |||||
| 2HER | Herramienta menor | (%)mo | 0.000300 | $41.24 | $0.01 |
| Suma de Herramienta | $0.01 | ||||
| Auxiliar | |||||
| HA182 | Mortero cemento-arena 1:3 | m3 | 0.001500 | $863.35 | $1.30 |
| Suma de Auxiliar | $1.30 | ||||
| Costo Directo | $84.73 |