Material |
|
|
|
|
MAC70 |
Defensa metal galvanizado cal. 12. |
m |
7.620000 |
$370.00 |
$2,819.40 |
MAC132 |
Separador galvanizado cal. 12. |
pza |
2.000000 |
$42.78 |
$85.56 |
MAC142 |
Terminal galvanizada cal. 10. |
pza |
1.000000 |
$215.00 |
$215.00 |
MAC144 |
Tornillo galvanizado 5/8″ x 1 1/4″ |
pza |
8.000000 |
$2.83 |
$22.64 |
MAC144 |
Tornillo galvanizado 5/8″ x 1 1/4″ |
pza |
2.000000 |
$2.83 |
$5.66 |
|
Suma de Material |
|
|
|
$3,148.26 |
|
Mano de Obra |
|
|
|
|
CUC2 |
Cuadrilla No. 2: peón + 1/10 cabo |
jor |
0.333300 |
$342.67 |
$114.21 |
|
Suma de Mano de Obra |
|
|
|
$114.21 |
|
Herramienta |
|
|
|
|
HEC1 |
Herramienta menor |
(%)mo |
0.030000 |
$114.21 |
$3.43 |
|
Suma de Herramienta |
|
|
|
$3.43 |
|
Auxiliar |
|
|
|
|
AUC52 |
2) En material “B” |
m3 |
0.007200 |
$163.53 |
$1.18 |
AUC63 |
Perfil estructural rectangular P.T.R., incluye valor de adquisicion, carga + descarga + acarreo al 1er. km y 9 kms. subsecuentes. |
kg |
12.261900 |
$14.17 |
$173.75 |
|
Suma de Auxiliar |
|
|
|
$174.93 |
|
Costo Directo |
|
|
|
$3,440.83 |