Clave | Descripción del Análisis de Precio Unitario | Unidad |
B10025A010 | Cimbra comun p/banquetas y pavimentos | m2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
MACMF150 | Polin 3 1/4″x3 1/4″x8 1/4′ | pt | 2.275000 | $6.20 | $14.11 |
A4DAR030 | Clavo de 2 1/2″, marca De Acero | kg | 0.075000 | $21.06 | $1.58 |
A4BAR012 | Alambre recocido Calibre 18 | kg | 0.058500 | $12.17 | $0.71 |
H7BPL005 | Diesel | L | 0.500000 | $5.06 | $2.53 |
Suma de Material | $18.93 | ||||
Mano de Obra | |||||
1ACCO | Carpintero para cimbras | Jor | 0.063300 | $345.77 | $21.89 |
1AA01 | Ayudante general | Jor | 0.063300 | $229.51 | $14.53 |
1AA00 | Peón | Jor | 0.017500 | $227.31 | $3.98 |
1AZC1 | Cabo de oficiales | jor | 0.006300 | $518.10 | $3.26 |
Suma de Mano de Obra | $43.66 | ||||
Herramienta | |||||
2HER | Herramienta menor | (%)mo | 0.000300 | $43.66 | $0.01 |
Suma de Herramienta | $0.01 | ||||
Costo Directo | $62.60 |