| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| HA111 | Acero de refuerzo no 2 (1/4") fy=2650 kg/cm2 | t |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| A1AAR015 | Alambron 1/4" No. 2 | t | 1.100000 | $8,000.00 | $8,800.00 |
| Suma de Material | $8,800.00 | ||||
| Mano de Obra | |||||
| 1AFRO | Fierrero | Jor | 9.281000 | $345.77 | $3,209.09 |
| 1AA01 | Ayudante general | Jor | 9.281000 | $229.51 | $2,130.08 |
| 1AA00 | Peón | Jor | 1.475000 | $227.31 | $335.28 |
| 1AZC1 | Cabo de oficiales | jor | 0.928100 | $518.10 | $480.85 |
| Suma de Mano de Obra | $6,155.30 | ||||
| Herramienta | |||||
| 2HER | Herramienta menor | (%)mo | 0.030000 | $6,155.30 | $184.66 |
| Suma de Herramienta | $184.66 | ||||
| Costo Directo | $15,139.96 |