| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 7153 | c) SR-9 a SR-33. | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| MAC143 | Tornillo galvanizado de 3" x 1/8" | pza | 2.000000 | $0.38 | $0.76 |
| MAC77 | Estopa | kg | 0.030000 | $37.50 | $1.13 |
| MAC12 | Adelgazador thinner | l | 0.300000 | $45.91 | $13.77 |
| MAC125 | Primario Anticorrosivo | l | 0.120000 | $104.31 | $12.52 |
| MAC147 | Tinta serigrafica negra | lto | 0.160000 | $14.50 | $2.32 |
| MAC148 | Thinner 711 p/tinta serigrafica | lto | 0.090000 | $37.73 | $3.40 |
| MAC197 | Papel Kraft | kg | 0.030000 | $10.95 | $0.33 |
| MAC128 | Scotch lite grado ingenieria blanco | m2 | 0.409300 | $177.93 | $72.83 |
| MAC34 | Bajo alfombra poli-pad | m2 | 0.050000 | $13.79 | $0.69 |
| MAC135 | Soldadura E-7018 | kg | 0.060000 | $35.00 | $2.10 |
| Suma de Material | $109.85 | ||||
| Mano de Obra | |||||
| CUC7 | Cuadrilla No. 7: oficial especialista + ayudante | jor | 0.120500 | $871.23 | $104.98 |
| CUC2 | Cuadrilla No. 2: peón + 1/10 cabo | jor | 0.120500 | $342.67 | $41.29 |
| MOC34 | Operario especialista | jor | 0.120500 | $575.85 | $69.39 |
| Suma de Mano de Obra | $215.66 | ||||
| Herramienta | |||||
| HEC1 | Herramienta menor | (%)mo | 0.030000 | $215.66 | $6.47 |
| Suma de Herramienta | $6.47 | ||||
| Equipo | |||||
| CHC119 | Compresor de 375 pcm, 122 hpmod. xa 175 atlas copeo (chicago pneumatic de 315 pcm 140 HP) | hr | 0.086400 | $190.37 | $16.45 |
| CHC120 | Dobladora y cortadora de lamina y placa hasta 25mm de espesor Espamex PT 50-50 | hr | 0.120500 | $172.18 | $20.75 |
| CHC121 | Taladro eléctrico manual bosh mod. 1182 | hr | 0.120500 | $1.87 | $0.23 |
| CHC121 | Taladro eléctrico manual bosh mod. 1182 | hr | 0.060500 | $1.87 | $0.11 |
| CHC81 | Soldadora Lincoln SAE 300 amp. K1277 mot. Perkins 4236, 4 cil., 60 HP, 1600 rpm., (sin operador). | hr | 0.151300 | $103.23 | $15.62 |
| CHC114 | Camioneta Pick-Up Ford F-250 8 cilindros 1.5 ton. 85 HP | hr | 0.052600 | $265.87 | $13.98 |
| Suma de Equipo | $67.14 | ||||
| Auxiliar | |||||
| AUC52 | 2) En material "B" | m3 | 0.080000 | $163.53 | $13.08 |
| AUC67 | Plantilla de grava de 6 cm para zapatas de concreto. | m2 | 0.164800 | $42.62 | $7.02 |
| AUC301 | Concreto f'c = 200 kg/cm² hecho in-situ agreg. max. 38mm producidos por el contratista. | m3 | 0.080000 | $1,457.02 | $116.56 |
| AUC610 | Acero de refuerzo No. 3 (3/8" diam.) fy= 4200 kg/cm2; incluye costo de adquisicion,carga y descarga + acarreo al1er km, y acarreo en 49kms subsecuentes >>3 varillas*1.8m*0.557kg/m*1.03desp=>>3.098 kg | ton | 0.000500 | $9,625.92 | $4.81 |
| AUC48 | Lamina galvanizada cal. 16; incluye valor de adquisición carga + descarga + acarreo al 1er km y 49kms. subsecuentes. | t | 0.004700 | $14,461.76 | $67.97 |
| AUC63 | Perfil estructural rectangular P.T.R., incluye valor de adquisicion, carga + descarga + acarreo al 1er. km y 9 kms. subsecuentes. | kg | 12.158100 | $14.17 | $172.28 |
| Suma de Auxiliar | $381.72 | ||||
| Costo Directo | $780.84 |