Clave | Descripción del Análisis de Precio Unitario | Unidad |
HA174 | Concreto f’c=300 kg/cm2, r.n., tma 19mm (3/4″), hecho en obra c/revolvedora | m3 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
ACACT055 | Cemento Tolteca CPC 30 R (cemento portland compuesto) | t | 0.449000 | $1,373.91 | $616.89 |
BAGRE0587 | Arena de rio (cribada) l.a.b. banco | M3 | 0.542000 | $36.30 | $19.67 |
BAGRE0213 | Material p/carpeta 19mm. (3/4″) -finos l.a.b. banco | M3 | 0.662000 | $45.00 | $29.79 |
ACMXX005 | Agua | m3 | 0.253000 | $85.00 | $21.51 |
Suma de Material | $687.86 | ||||
Auxiliar | |||||
HA169 | Elaboracion concreto obra c/revolvedora | m3 | 1.000000 | $174.84 | $174.84 |
Suma de Auxiliar | $174.84 | ||||
Costo Directo | $862.70 |