| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| A15020A020 | Obra falsa para superestructura de puentes | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| MACMF150 | Polin 3 1/4"x3 1/4"x8 1/4' | pt | 9.333300 | $6.20 | $57.87 |
| A4DAR030 | Clavo de 2 1/2", marca De Acero | kg | 0.250000 | $21.06 | $5.27 |
| A4BAR012 | Alambre recocido Calibre 18 | kg | 0.250000 | $12.17 | $3.04 |
| Suma de Material | $66.18 | ||||
| Mano de Obra | |||||
| 1ACCO | Carpintero para cimbras | Jor | 0.245000 | $345.77 | $84.71 |
| 1AA01 | Ayudante general | Jor | 0.245000 | $229.51 | $56.23 |
| 1AA00 | Peón | Jor | 0.024500 | $227.31 | $5.57 |
| 1AZC1 | Cabo de oficiales | jor | 0.024500 | $518.10 | $12.69 |
| Suma de Mano de Obra | $159.20 | ||||
| Herramienta | |||||
| 2HER | Herramienta menor | (%)mo | 0.000300 | $159.20 | $0.05 |
| Suma de Herramienta | $0.05 | ||||
| Costo Directo | $225.43 |