| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| A25025A120 | Tuberia de concreto reforzado de f'c = 280 kg/cm2 de: -91 cm. de diametro grado 4. | m |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| TCN04006 | Tubo de 91 cm (36") de diametro, 2.50m de largo, (2.44m de largo util) de concreto reforzado Norma S.C.T., Grado S.C.T. Marca Cocomsa. | pza | 1.010000 | $3,575.00 | $3,610.75 |
| MACMF150 | Polin 3 1/4"x3 1/4"x8 1/4' | pt | 1.015000 | $6.20 | $6.29 |
| BOIAVA025 | Cable manila 1" 2.5 ml x kg. | kg | 0.109000 | $29.56 | $3.22 |
| ACMXX005 | Agua | m3 | 0.089000 | $85.00 | $7.57 |
| Suma de Material | $3,627.83 | ||||
| Mano de Obra | |||||
| 1ATP4 | Estadalero | Jor | 0.075000 | $227.31 | $17.05 |
| 1ATBY | Ayudante de tubero | Jor | 0.300000 | $227.31 | $68.19 |
| 1AABO | Albañil | Jor | 0.075000 | $372.63 | $27.95 |
| 1AA00 | Peón | Jor | 0.150000 | $227.31 | $34.10 |
| 1AZC1 | Cabo de oficiales | jor | 0.061000 | $518.10 | $31.60 |
| Suma de Mano de Obra | $178.89 | ||||
| Herramienta | |||||
| 2HER | Herramienta menor | (%)mo | 0.000300 | $178.89 | $0.05 |
| Suma de Herramienta | $0.05 | ||||
| Equipo | |||||
| EQHA135-350 | Tripie metálico con garrucha para 2 ton. | hr | 0.666700 | $1.48 | $0.99 |
| EQHA135-605 | Grua marca Hiab modelo 035/2 para 510 kg en camion de 3.5 t marca Dodge 3500 6 ton. | hr | 0.233300 | $171.40 | $39.99 |
| Suma de Equipo | $40.98 | ||||
| Auxiliar | |||||
| HA182 | Mortero cemento-arena 1:3 | m3 | 0.023000 | $863.35 | $19.86 |
| Suma de Auxiliar | $19.86 | ||||
| Costo Directo | $3,867.61 |