Clave | Descripción del Análisis de Precio Unitario | Unidad |
4122-32 | COLUMNA DE CONCRETO F’c=200 KG/CM2, DE 30 CM DE DIAMETRO A BASE, ARMADO CON Vs # 4 Y EST #2 @ 20 CMS INCLUYE CIMBRA Y DESCIMBRA | PZA |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 11.600000 | $16.15 | $187.34 |
CLAVO 1/2″ 1 | CLAVO 1/2″ | KG | 0.450000 | $34.00 | $15.30 |
ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.300000 | $19.00 | $5.70 |
DIESEL 1 | DIESEL | LTO | 0.800000 | $11.28 | $9.02 |
Suma de Material | $217.36 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.120000 | $307.31 | $36.88 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 1.200000 | $251.32 | $301.58 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 1.200000 | $197.97 | $237.56 |
OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 1.200000 | $185.16 | $222.19 |
Suma de Mano de Obra | $798.21 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $798.21 | $23.95 |
Suma de Herramienta | $23.95 | ||||
Auxiliar | |||||
ACERO REF #4 1 | ACERO DE REFUERZO # 4 | KG. | 11.000000 | $18.30 | $201.30 |
ALAMBRON #2 1 | ALAMBRON DE 1/4″ | KG | 8.000000 | $20.06 | $160.48 |
CONCRETO F-C=200 1 | CONCRETO F’c=200 KG/CM2 | M3 | 0.260000 | $1,322.37 | $343.82 |
VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.260000 | $230.70 | $59.98 |
Suma de Auxiliar | $765.58 | ||||
Costo Directo | $1,805.10 |