Clave | Descripción del Análisis de Precio Unitario | Unidad |
4121-01 | DADO DE CONCRETO PREMEZCLADO F’c=200 KG/CM2, SECCION 30 x 40 CM ARMADO CON 12 Vs # 4 Y EST #3 @ 30 CMS INCLUYE CIMBRA Y DESCIMBRA | ML |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 7.800000 | $16.15 | $125.97 |
CLAVO 1/2″ 1 | CLAVO 1/2″ | KG | 0.160000 | $34.00 | $5.44 |
ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.100000 | $19.00 | $1.90 |
DIESEL 1 | DIESEL | LTO | 0.400000 | $11.28 | $4.51 |
CHAF P/MAD 1 | CHAFLAN PARA MADERA DE 1″ | M | 4.000000 | $2.50 | $10.00 |
CONC PREM 200 1 | CONCRETO PREMEZCLADO F’c=200 KG/CM2 | M3 | 0.120000 | $1,109.86 | $133.18 |
Suma de Material | $281.00 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.006670 | $307.31 | $2.05 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.066670 | $251.32 | $16.76 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.066670 | $197.97 | $13.20 |
OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.066670 | $185.16 | $12.34 |
Suma de Mano de Obra | $44.35 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $44.35 | $1.33 |
Suma de Herramienta | $1.33 | ||||
Auxiliar | |||||
ACERO REF #4 1 | ACERO DE REFUERZO # 4 | KG. | 12.000000 | $18.30 | $219.60 |
ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 6.000000 | $23.47 | $140.82 |
VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.120000 | $230.70 | $27.68 |
Suma de Auxiliar | $388.10 | ||||
Costo Directo | $714.78 |