Clave | Descripción del Análisis de Precio Unitario | Unidad |
6023-13 | DISTRIBUCION DE CIRCUITO ELECTRICO INCLUYE TUBERIA CONDUIT DE PARED DELGADA DE 1/2″, 3/4″ Y 1″ , CAJA CHALUPA Y CABLE CAL # 12 Y 14, HERRAMIENTA, EQUIPO, MATERIAL Y MANO DE OBRA NECESARIA | ML |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
TUBO COND 1/2″ 1 | TUBO CONDUIT 1/2″ GALVANIZADO P/GRUESA | M | 1.100000 | $52.33 | $57.56 |
TUBO COND 3/4″ 1 | TUBO CONDUIT 3/4″ GALVANIZADO P/GRUESA | M | 1.100000 | $70.13 | $77.14 |
TUBO COND 1″ 1 | TUBO CONDUIT 1″ GALVANIZADO P/GRUESA | M | 1.100000 | $79.20 | $87.12 |
CAJA CHAL 4″ 1 | CAJA CHALUPA 4″ | PZA | 0.250000 | $8.80 | $2.20 |
CABLE # 12 1 | CABLE THWN CAL # 12 | M | 1.100000 | $6.45 | $7.10 |
CABLE # 14 1 | CABLE THWN CAL # 14 | M | 1.100000 | $4.38 | $4.82 |
Suma de Material | $235.94 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.005000 | $307.31 | $1.54 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.050000 | $251.32 | $12.57 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.050000 | $197.97 | $9.90 |
Suma de Mano de Obra | $24.01 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $24.01 | $0.72 |
Suma de Herramienta | $0.72 | ||||
Costo Directo | $260.67 |