Clave | Descripción del Análisis de Precio Unitario | Unidad |
2068-17 | GABINETE DE ACERO INOXIDABLE PARA CONEXION DE SENSOR, INSTALACION CON PEDESTAL DE PTR DE 3″ INCLUYE REGISTROS CONDULET, TUBERIA GALVANIZADA PARED GRUESA DE 1/2″, TUBERIA LIQUATITE E INSTALACION DE CABLEADO | PZA |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
GAB AC INOX SENSOR 1 | GABINETE DE ACERO INOXIDABLE PARA SENSOR | PZA | 1.000000 | $3,255.00 | $3,255.00 |
PTR ESTRUCTURAL 3″ 1 | PTR ESTRUCTURAL DE 3″ | KG | 33.000000 | $18.00 | $594.00 |
TUBO ACERO GALV 1/2″ | TUBO DE ACERO GALVANIZADO DE 1/2″ | M | 4.000000 | $52.33 | $209.32 |
TUBO LICUATITE 1/2″ | TUBO DE LICUATITE DE 1/2″ DE DIAMETRO | M | 2.000000 | $17.75 | $35.50 |
SOLDADURA E-7018 1 | SOLDADURA E-7018 | KG | 3.000000 | $49.88 | $149.64 |
PINTURA ANTICORR 1 | PINTURA ANTICORROSIVA | LTO | 0.500000 | $90.00 | $45.00 |
PINT ESMALTE 1 | PINTURA ESMALTE | LTO | 0.500000 | $90.00 | $45.00 |
THINER 1 | THINER PARA PINTURA EPOXIMASTIC | LTO | 0.500000 | $40.00 | $20.00 |
MAS DESECHABLES 1 | MASCARILLA DESECHABLES | PZA | 1.000000 | $11.30 | $11.30 |
CAP ALG PINTAR 1 | CAPUCHA DE ALGODON PARA PINTAR (SPRAY SOCK) | PZA | 1.000000 | $34.00 | $34.00 |
LENTES DE SEG 1 | LENTE DE SEGURIDAD | PZA | 1.000000 | $46.80 | $46.80 |
LIJA GRUESA 1 | LIJA GRUESA | PZA | 4.000000 | $11.00 | $44.00 |
ESTOPA 2A 1 | ESTOPA SEGUNDA | KG | 1.000000 | $52.00 | $52.00 |
PLACA DE ACERO 1/2″1 | PLACA DE ACERO DE 1/2″ | KG | 10.000000 | $12.50 | $125.00 |
TORNILLO 1/4″X1″ 1 | TORNILLO DE 1/4″ x 1″ | PZA | 8.000000 | $4.00 | $32.00 |
DISCO PULIDORA 1 | DISCO DE PULIDORA | PZA | 0.500000 | $68.00 | $34.00 |
PER ANC 3/4″X 5 1/2″ | PERNO ANCLA ARPON DE 3/4″ x 5 1/2″ | PZA | 4.000000 | $37.60 | $150.40 |
BROCA DE 3/4″ 1 | BROCA DE 3/4″ | PZA | 1.000000 | $88.00 | $88.00 |
Suma de Material | $4,970.96 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.060000 | $307.31 | $18.44 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.600000 | $251.32 | $150.79 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.600000 | $197.97 | $118.78 |
OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.600000 | $185.16 | $111.10 |
Suma de Mano de Obra | $399.11 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $399.11 | $11.97 |
Suma de Herramienta | $11.97 | ||||
Equipo | |||||
PLANTA SOLDAR 1 | PLANTA DE SOLDAR DE GASOLINA | HORA | 4.000000 | $113.61 | $454.44 |
EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 4.000000 | $26.43 | $105.72 |
CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 1.000000 | $202.91 | $202.91 |
Suma de Equipo | $763.07 | ||||
Costo Directo | $6,145.11 |