| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4120-36 | SUMINISTRO Y COLOCACION DE PUERTA REJA DEACERO DE 5.00 x 2.00 M DE ALTURA INCLUYE TUBERIA REJA VERDE, RIEL ANGULO, RUEDA GUIA, RODILLO DE HULE, PORTA CANDADO, ACCESORIOS, MATERIALES, MANO DE OBRA Y HERRAMIENTA | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| PUERTA REJA 5.0*2.0 | PUERTA REJA DEACERO DE 5.00 x 2.00 M | PZA | 1.000000 | $12,015.00 | $12,015.00 |
| TUB REJA 2 1/4"*2.5 | TUBERIA REJA VERDE DE 2 1/4" x 2.50 M | PZA | 2.000000 | $411.17 | $822.34 |
| TUBO AC GALV 1 3/8" | TUBO GALVANIZADO DE 1 3/8" | M | 5.000000 | $23.56 | $117.80 |
| PUERTA REJA 1.0*2.0 | PUERTA REJA DEACERO DE 1.00 x 2.00 M | PZA | 1.000000 | $2,714.36 | $2,714.36 |
| RIEL ANG 1/4"*1 1/4" | RIEL ANGULO DE 1/4" x 1 1/4" | ML | 10.500000 | $81.66 | $857.43 |
| RUEDA GUIA EMB 4" 1 | RUEDA GUIA EMBALERADA DE 4" | PZA | 2.000000 | $620.00 | $1,240.00 |
| RODILLO HULE 3" | RODILLO DE HULE LATERAL PARA PORTON 3" | PZA | 2.000000 | $177.84 | $355.68 |
| PORTA CANDADO 60*48 | PORTA CANDADO DE 60 x 48 CM | PZA | 2.000000 | $46.50 | $93.00 |
| FLANGE 10"X15"-3/16" | FLANGE 10" x 15"-3/16" | PZA | 4.000000 | $50.00 | $200.00 |
| EXPANSOR 3/8"X3" | EXPANSION DE 3/8" x 3" | PZA | 16.000000 | $13.31 | $212.96 |
| Suma de Material | $18,628.57 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.200000 | $307.31 | $61.46 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 2.000000 | $251.32 | $502.64 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 2.000000 | $197.97 | $395.94 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 2.500000 | $185.16 | $462.90 |
| Suma de Mano de Obra | $1,422.94 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $1,422.94 | $42.69 |
| Suma de Herramienta | $42.69 | ||||
| Equipo | |||||
| CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 0.500000 | $202.91 | $101.46 |
| Suma de Equipo | $101.46 | ||||
| Auxiliar | |||||
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 0.080000 | $75.29 | $6.02 |
| CONCRETO F-C=150 1 | CONCRETO F'c=150 KG/CM2 | M3 | 0.095000 | $1,181.52 | $112.24 |
| Suma de Auxiliar | $118.26 | ||||
| Costo Directo | $20,313.92 |