Clave | Descripción del Análisis de Precio Unitario | Unidad |
4122-08 | CADENA DE CONCRETO F’c=150 KG/CM2, SECCION 15 x 20 CM, ARMADO CON 4 Vs # 4 Y EST #2 @ 20 CMS INCLUYE CIMBRA Y DESCIMBRA | ML |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 3.500000 | $16.15 | $56.53 |
CLAVO 1/2″ 1 | CLAVO 1/2″ | KG | 0.070000 | $34.00 | $2.38 |
ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.030000 | $19.00 | $0.57 |
DIESEL 1 | DIESEL | LTO | 0.300000 | $11.28 | $3.38 |
CHAF P/MAD 1 | CHAFLAN PARA MADERA DE 1″ | M | 4.000000 | $2.50 | $10.00 |
Suma de Material | $72.86 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.005000 | $307.31 | $1.54 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.050000 | $251.32 | $12.57 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.050000 | $197.97 | $9.90 |
OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.050000 | $185.16 | $9.26 |
Suma de Mano de Obra | $33.27 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $33.27 | $1.00 |
Suma de Herramienta | $1.00 | ||||
Auxiliar | |||||
ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 2.400000 | $23.47 | $56.33 |
ALAMBRON #2 1 | ALAMBRON DE 1/4″ | KG | 1.000000 | $20.06 | $20.06 |
CONCRETO F-C=150 1 | CONCRETO F’c=150 KG/CM2 | M3 | 0.030000 | $1,181.52 | $35.45 |
VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.030000 | $230.70 | $6.92 |
Suma de Auxiliar | $118.76 | ||||
Costo Directo | $225.89 |