Clave | Descripción del Análisis de Precio Unitario | Unidad |
2068-97 | SUMINISTRO E INSTALACION DE CANAL DE 6″ X 12.20 KG/M INCLUYE HABILITADO Y MONTAJE | KG |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
CANAL 6″X12.20 KG/M | CANAL DE 6″ x 12.20 KG/M | KG | 1.100000 | $14.70 | $16.17 |
ACETILENO 1 | ACETILENO | KG | 0.030000 | $130.00 | $3.90 |
OXIGENO 1 | OXIGENO | M3 | 0.040000 | $39.00 | $1.56 |
SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 0.050000 | $49.88 | $2.49 |
PINTURA ANTICORR 1 | PINTURA ANTICORROSIVA | LTO | 0.007000 | $90.00 | $0.63 |
Suma de Material | $24.75 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.001750 | $307.31 | $0.54 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.017500 | $251.32 | $4.40 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.017500 | $197.97 | $3.46 |
OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.017500 | $185.16 | $3.24 |
Suma de Mano de Obra | $11.64 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $11.64 | $0.35 |
Suma de Herramienta | $0.35 | ||||
Equipo | |||||
PLANTA SOLDAR 1 | PLANTA DE SOLDAR DE GASOLINA | HORA | 0.030000 | $113.61 | $3.41 |
EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 0.030000 | $26.43 | $0.79 |
CAMION WINCHE 1 | CAMION WINCHE FORD DE 5 TON DE CAPACIDAD | HORA | 0.008000 | $285.24 | $2.28 |
Suma de Equipo | $6.48 | ||||
Costo Directo | $43.22 |