| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4122-33 | CERRAMIENTO DE CONCRETO F'c=150 KG/CM2, SECCION 15 x 20 CM, ARMADO CON ARMEX DE 15x20-4 y 2 VARILLA #3 INCLUYE CIMBRA Y DESCIMBRA, MATERIALES, MANO DE OBRA, EQUIPO Y HERRAMIENTA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 4.800000 | $16.15 | $77.52 |
| CLAVO 1/2" 1 | CLAVO 1/2" | KG | 0.100000 | $34.00 | $3.40 |
| ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.060000 | $19.00 | $1.14 |
| DIESEL 1 | DIESEL | LTO | 0.600000 | $11.28 | $6.77 |
| ARMEX 15*20-4 | ARMEX 15-20-4 | M | 1.000000 | $31.00 | $31.00 |
| Suma de Material | $119.83 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.006250 | $307.31 | $1.92 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.062500 | $251.32 | $15.71 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.062500 | $197.97 | $12.37 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.062500 | $185.16 | $11.57 |
| Suma de Mano de Obra | $41.57 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $41.57 | $1.25 |
| Suma de Herramienta | $1.25 | ||||
| Auxiliar | |||||
| CONCRETO F-C=150 1 | CONCRETO F'c=150 KG/CM2 | M3 | 0.030000 | $1,181.52 | $35.45 |
| VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.030000 | $230.70 | $6.92 |
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 1.114000 | $23.47 | $26.15 |
| Suma de Auxiliar | $68.52 | ||||
| Costo Directo | $231.17 |