| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| 2068-18 | SUMINISTRO E INSTALACION DE VALVULA DE ADMISION Y EXPULSION DE AIRE DE 3" DE DIAMETRO, VALVULA DE COMPUERTA DE 3" DE DIAMETRO PARA AGUAS RESIDUALES, FLANCHS, TORNILLERIA DE ACERO INOXIDABLE, NIPLES ROSACADOS, APLICACION DE SANDELASTEO Y PINTURA EPOXICA | PZA |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| VAL ADM Y EXP 3" 1 | VALVULA DE ADMISION Y EXPULSION DE 3" DE DIAMETRO | PZA | 1.000000 | $1,671.00 | $1,671.00 |
| VAL COMPUERTA 3" 1 | VALVULA DE COMPUERTA DE 3" DE DIAMETRO | PZA | 1.000000 | $2,331.00 | $2,331.00 |
| PINTURA EPOXICA 1 | PRIMARIO EPOXICO RP-6 | LTO | 0.500000 | $85.00 | $42.50 |
| TORNILLO 5/8"X3" 1 | TORNILLO DE 5/8" x 3" | PZA | 8.000000 | $23.00 | $184.00 |
| COPLE GALV 3" 1 | COPLE DE ACERO GALVANIZADO DE 3" | PZA | 1.000000 | $134.41 | $134.41 |
| BRIDA ACERO 3" 1 | BRIDA DE ACERO DE 3" DE DIAMETRO PARA 125 LBS | PZA | 2.000000 | $256.00 | $512.00 |
| EMPAQUE NEOP 3" 1 | EMPAQUE DE NEOPRENO ROJO DE 3/16" x 3" | PZA | 2.000000 | $41.00 | $82.00 |
| NIPLE ACERO 3" 1 | NIPLE DE ACERO GALVANIZADO DE 3" | PZA | 2.000000 | $108.76 | $217.52 |
| THINER 1 | THINER PARA PINTURA EPOXIMASTIC | LTO | 2.000000 | $40.00 | $80.00 |
| MAS DESECHABLES 1 | MASCARILLA DESECHABLES | PZA | 1.000000 | $11.30 | $11.30 |
| CAP ALG PINTAR 1 | CAPUCHA DE ALGODON PARA PINTAR (SPRAY SOCK) | PZA | 1.000000 | $34.00 | $34.00 |
| LENTES DE SEG 1 | LENTE DE SEGURIDAD | PZA | 1.000000 | $46.80 | $46.80 |
| LIJA GRUESA 1 | LIJA GRUESA | PZA | 1.000000 | $11.00 | $11.00 |
| ESTOPA 2A 1 | ESTOPA SEGUNDA | KG | 1.000000 | $52.00 | $52.00 |
| Suma de Material | $5,409.53 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.080000 | $307.31 | $24.58 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.800000 | $251.32 | $201.06 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.800000 | $197.97 | $158.38 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.800000 | $185.16 | $148.13 |
| Suma de Mano de Obra | $532.15 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $532.15 | $15.96 |
| Suma de Herramienta | $15.96 | ||||
| Equipo | |||||
| PLANTA DE LUZ 1 | PLANTA DE LUZ DE 15 KW | HORA | 4.000000 | $39.75 | $159.00 |
| PLANTA SOLDAR 1 | PLANTA DE SOLDAR DE GASOLINA | HORA | 4.000000 | $113.61 | $454.44 |
| EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 4.000000 | $26.43 | $105.72 |
| CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 2.000000 | $202.91 | $405.82 |
| Suma de Equipo | $1,124.98 | ||||
| Costo Directo | $7,082.62 |