Clave | Descripción del Análisis de Precio Unitario | Unidad |
4123-38 | LOSA DE CONCRETO PREMEZCLADO F’c=200 KG/CM2 DE 4 CM DE ESPESOR, ALIGERADA CON VIGUETA Y BOVEDILLA CON MALLA ELECTROSOLDADA INCLUYE CIMBRA Y DESCIMBRA Y CURADO | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
VIGUETA PRETENSADA | VIGUETA PRETENSADA PERFIL 16 | M | 2.300000 | $41.88 | $96.32 |
BOVEDILLA CONC 16/17 | BOVEDILLA DE CONCRETO 16/17 | PZA | 7.900000 | $10.20 | $80.58 |
MALLA ELEC 10-10/6-6 | MALLA ELECTROSOLDADA 6-6/10-10 | M2 | 1.100000 | $10.34 | $11.37 |
CONC PREM 200 C/BOM | CONCRETO PREMEZCLADO F’c=200 KG/CM2 CON BOMBEABLE | M3 | 0.040000 | $1,168.90 | $46.76 |
MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 4.330000 | $16.15 | $69.93 |
CLAVO 1/2″ 1 | CLAVO 1/2″ | KG | 0.280000 | $34.00 | $9.52 |
Suma de Material | $314.48 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.009000 | $307.31 | $2.77 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.090000 | $251.32 | $22.62 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.090000 | $197.97 | $17.82 |
OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.170000 | $185.16 | $31.48 |
Suma de Mano de Obra | $74.69 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $74.69 | $2.24 |
Suma de Herramienta | $2.24 | ||||
Costo Directo | $391.41 |