Clave | Descripción del Análisis de Precio Unitario | Unidad |
2068-47 | SUMINISTRO Y FABRICACION DE RACKS A BASE DE ESTRUCTURA METALICA TIPO IPR DE 6″ COMO CARGADORES Y POLINES TIPO MONTEN PARA CARGADORES DE TRIPLAY DE 3/4″ PARA PISO CON SEPARACION ENTRE RACKS DE 1.20 Y UNA ALTURA MAXIMA DE 4 M LARGO CON TRES ENTREPAÑOS | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
VIGA IPR DE 6″X4″ 1 | VIGA IPR DE 6″X4″ (13.40 KG/M) | KG | 25.000000 | $16.00 | $400.00 |
POLIN TIPO MONTEN 6″ | POLIN TIPO MONTEN 6″ MT 12 | KG | 40.000000 | $14.70 | $588.00 |
ACETILENO 1 | ACETILENO | KG | 1.500000 | $130.00 | $195.00 |
OXIGENO 1 | OXIGENO | M3 | 2.500000 | $39.00 | $97.50 |
SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 3.500000 | $49.88 | $174.58 |
PINTURA ANTICORR 1 | PINTURA ANTICORROSIVA | LTO | 2.000000 | $90.00 | $180.00 |
HOJA TRIPLAY 3/4″ 1 | HOJA DE TRIPLAY 3/4″ 1 CARA | HOJA | 1.000000 | $288.00 | $288.00 |
PIJAS P/BROCA 1 | PIJA P/BROCA AME DE 1/4″ x 7/8″ | PZA | 35.000000 | $1.50 | $52.50 |
Suma de Material | $1,975.58 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.017500 | $307.31 | $5.38 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.175000 | $251.32 | $43.98 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.175000 | $197.97 | $34.64 |
OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.175000 | $185.16 | $32.40 |
Suma de Mano de Obra | $116.40 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $116.40 | $3.49 |
Suma de Herramienta | $3.49 | ||||
Equipo | |||||
PLANTA SOLDAR 1 | PLANTA DE SOLDAR DE GASOLINA | HORA | 0.300000 | $113.61 | $34.08 |
EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 0.300000 | $26.43 | $7.93 |
CAMION WINCHE 1 | CAMION WINCHE FORD DE 5 TON DE CAPACIDAD | HORA | 0.080000 | $285.24 | $22.82 |
Suma de Equipo | $64.83 | ||||
Costo Directo | $2,160.30 |