| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4080-11 | CIMBRA ACABADO APARENTE EN COLUMNA CON TRIPLAY DE 16 MM INCLUYE HABILITADO, CIMBRADO Y DESCIMBRADO | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| TRIPLAY 16 MM 1 | TRIPLAY DE PINO DE 16 MM DE ESPESOR | M2 | 0.140000 | $112.00 | $15.68 |
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 4.200000 | $16.15 | $67.83 |
| CLAVO 1/2" 1 | CLAVO 1/2" | KG | 0.130000 | $34.00 | $4.42 |
| ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.100000 | $19.00 | $1.90 |
| DIESEL 1 | DIESEL | LTO | 0.500000 | $11.28 | $5.64 |
| CHAF P/MAD 1 | CHAFLAN PARA MADERA DE 1" | M | 1.100000 | $2.50 | $2.75 |
| Suma de Material | $98.22 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.013890 | $307.31 | $4.27 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.138890 | $251.32 | $34.91 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.138890 | $197.97 | $27.50 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.069440 | $185.16 | $12.86 |
| Suma de Mano de Obra | $79.54 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $79.54 | $2.39 |
| Suma de Herramienta | $2.39 | ||||
| Equipo | |||||
| CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 0.022220 | $202.91 | $4.51 |
| Suma de Equipo | $4.51 | ||||
| Costo Directo | $184.66 |