| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4122-23 | VARILLA AHOGADA EN CONCRETO F'c=200 KG/CM2 CON VARILLA DE 3/8" | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 3.500000 | $16.15 | $56.53 |
| CLAVO 1/2" 1 | CLAVO 1/2" | KG | 0.075000 | $34.00 | $2.55 |
| ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.035000 | $19.00 | $0.67 |
| DIESEL 1 | DIESEL | LTO | 0.400000 | $11.28 | $4.51 |
| Suma de Material | $64.26 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.005000 | $307.31 | $1.54 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.050000 | $251.32 | $12.57 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.050000 | $197.97 | $9.90 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.050000 | $185.16 | $9.26 |
| Suma de Mano de Obra | $33.27 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $33.27 | $1.00 |
| Suma de Herramienta | $1.00 | ||||
| Auxiliar | |||||
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 1.200000 | $23.47 | $28.16 |
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 0.022500 | $1,322.37 | $29.75 |
| VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.022500 | $230.70 | $5.19 |
| Suma de Auxiliar | $63.10 | ||||
| Costo Directo | $161.63 |