| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1001-16 | FIRME DE CONCRETO PREMEZCLADO F'c=200 KG/CM2 DE 18 CM DE ESPESOR, ARMADO CON PARRILLA No 3 @ 30 CM Y ACABADO ESCOBILLADO | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| MALLA ELEC 6-6/6-6 1 | MALLA ELECTROSOLDADA 6-6/6-6 | M2 | 1.100000 | $24.60 | $27.06 |
| CONC PREM 200 C/BOM | CONCRETO PREMEZCLADO F'c=200 KG/CM2 CON BOMBEABLE | M3 | 0.180000 | $1,168.90 | $210.40 |
| Suma de Material | $237.46 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.003000 | $307.31 | $0.92 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.030000 | $251.32 | $7.54 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.030000 | $197.97 | $5.94 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.060000 | $185.16 | $11.11 |
| Suma de Mano de Obra | $25.51 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $25.51 | $0.77 |
| Suma de Herramienta | $0.77 | ||||
| Auxiliar | |||||
| CIM Y DESCIM 1 | CIMBRA Y DESCIMBRA | M2 | 0.200000 | $164.13 | $32.83 |
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 2.200000 | $23.47 | $51.63 |
| Suma de Auxiliar | $84.46 | ||||
| Costo Directo | $348.20 |