| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2068-93 | SUMINISTRO Y COLOCACION DE BARANDAL DE PROTECCION DE TINACO A BASE DE SOLERA 1 1/2" X 3/16" Y ANGULO DE 2" X 2" 1/8" INCLUYE HERRAMIENTA, EQUIPO, MATERIAL Y MANO DE OBRA NECESARIA | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| ACERO ESTR A-36 1 | ACERO ESTRUCTURAL A-36 | KG | 1.150000 | $16.00 | $18.40 |
| ACETILENO 1 | ACETILENO | KG | 0.046000 | $130.00 | $5.98 |
| OXIGENO 1 | OXIGENO | M3 | 0.049000 | $39.00 | $1.91 |
| SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 0.080000 | $49.88 | $3.99 |
| PINTURA ANTICORR 1 | PINTURA ANTICORROSIVA | LTO | 0.020000 | $90.00 | $1.80 |
| ADITIVO ANTIRUST 1 | ADITIVO PARA FRENAR CORROSION ANTIRUST | LTO | 0.015000 | $80.00 | $1.20 |
| Suma de Material | $33.28 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.002000 | $307.31 | $0.61 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.020000 | $251.32 | $5.03 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.020000 | $197.97 | $3.96 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.020000 | $185.16 | $3.70 |
| Suma de Mano de Obra | $13.30 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $13.30 | $0.40 |
| Suma de Herramienta | $0.40 | ||||
| Equipo | |||||
| PLANTA SOLDAR 1 | PLANTA DE SOLDAR DE GASOLINA | HORA | 0.050000 | $113.61 | $5.68 |
| EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 0.050000 | $26.43 | $1.32 |
| CAMION WINCHE 1 | CAMION WINCHE FORD DE 5 TON DE CAPACIDAD | HORA | 0.010000 | $285.24 | $2.85 |
| EQ SANDBLAST 1 | EQUIPO PARA SANDBAST CON ACCESORIOS | HORA | 0.050000 | $16.28 | $0.81 |
| Suma de Equipo | $10.66 | ||||
| Costo Directo | $57.64 |